Filling station CNG

Investor
DPmB
Type of order
Industrial construction
Realization date
march 2014 - july 2014
Amount
8 000 000 Kč
Place
Brno

For the investor Dopravní podnik Brno was done a reconstruction of the existing substation, a supply of a new transformer, a diesel generator, LV relocations and connections for the new CNG filling station. Powering of the CNG station is backed up from two places – from the existing substation and then the DA. The filling station is connected to a high-pressure gas connection and is able to fill up about 6 buses per hour.